The high-speed railway project on the
North-South axis section passing through 

00:00:06.465 --> 00:00:08.814 
Hue city is more than 65 km long, 

00:00:09.234 --> 00:00:13.258 
passing through 12 communes and wards,
resettlement areas, and dormitories 

00:00:13.258 --> 00:00:16.074 
serving the project started
in August 2025. 

00:00:16.734 --> 00:00:20.054 
Up to now, many projects have been
basically completed and have ensured progress. 

00:00:21.452 --> 00:00:24.169 
Ladies and gentlemen, the entire
resettlement area serving the 

00:00:24.169 --> 00:00:26.584 
North-South high-speed railway project
through Hue city is 

00:00:26.584 --> 00:00:27.792 
being focused on construction. 

00:00:28.332 --> 00:00:31.452 
In Phu Vang commune, the first company
has completed and is ready 

00:00:31.452 --> 00:00:32.752 
to deploy and use it. 

00:00:33.896 --> 00:00:37.696 
Recorded at Phu Da resettlement area,
Phu Vang commune, the project has a 

00:00:37.696 --> 00:00:41.203 
scale of nearly 5 hectares with 89
resettlement plots, with a total 

00:00:41.203 --> 00:00:42.956 
investment of about 44 billion VND. 

00:00:43.396 --> 00:00:47.556 
The project includes 3 bidding packages,
of which package No. 12 implements the 

00:00:47.556 --> 00:00:50.756 
items of foundation leveling,
transportation system, drainage and parking lot. 

00:00:50.876 --> 00:00:54.866 
Package No. 13 builds a water supply
system, package No. 15 implements 

00:00:54.866 --> 00:00:56.196 
the green tree item. 

00:00:56.196 --> 00:00:59.543 
According to the state representative
managing the area 3 construction 

00:00:59.543 --> 00:01:02.889 
investment project, the Phu Da
resettlement area project has been 

00:01:02.889 --> 00:01:04.896 
completed according to the drawing design. 

00:01:05.016 --> 00:01:08.856 
is approved and complies with current
technical regulations and standards. 

00:01:09.276 --> 00:01:11.723 
The State has requested the construction
appraisal sub-department under the 

00:01:11.723 --> 00:01:14.169 
Department of Construction to organize
the Inspection of Acceptance and 

00:01:14.169 --> 00:01:15.636 
Construction Works according to its authority. 

00:01:15.936 --> 00:01:20.308 
Currently, in Hue City, there are 33
infrastructure projects serving the 

00:01:20.308 --> 00:01:25.076 
North-South high-speed railway with a
total cost of about 1,807 billion VND. 

00:01:25.076 --> 00:01:29.721 
including 22 resettlement areas, 6
dormitory areas, 4 schools and 1 market 

00:01:29.721 --> 00:01:31.656 
area combined with resettlement project. 

00:01:32.056 --> 00:01:35.823 
Recorded at resettlement infrastructure
projects in Phu Ho commune and Vi Da 

00:01:35.823 --> 00:01:38.961 
ward, construction is also being
accelerated, and many important items 

00:01:38.961 --> 00:01:40.216 
have gradually been completed. 

00:01:42.199 --> 00:01:45.241 
Based on evaluation, they are very
aggressive, based on evaluation, 

00:01:45.241 --> 00:01:46.459 
they are very aggressive. 

00:01:47.599 --> 00:01:50.536 
The groundbreaking ceremony is right at
the groundbreaking ceremony, making a 

00:01:50.536 --> 00:01:52.139 
lot of soil in one day. 

00:01:53.379 --> 00:01:56.979 
Now that it's iced honey, it's enough,
temporarily it's available now. 

00:01:57.999 --> 00:02:02.593 
Thinking it's easy for them to do, easy
to do again, easy to return, loosen 

00:02:02.593 --> 00:02:03.819 
up, take the leap. 

00:02:04.796 --> 00:02:07.020 
Currently, investors are requesting
contractors to accelerate progress, 

00:02:07.020 --> 00:02:10.356 
striving to complete the block
separation milestone by the end of July. 

00:02:10.356 --> 00:02:15.216 
in order to soon complete synchronous
resettlement infrastructure, serving affected households 

00:02:15.216 --> 00:02:19.236 
due to site clearance for the high-speed
railway project on the North-South axis. 