Ladies and gentlemen, the project to
renovate the central canal section 

00:00:08.093 --> 00:00:11.126 
passing through An Nhon and Binh Loi
Trung wards has gradually taken shape. 

00:00:11.126 --> 00:00:15.186 
According to records of workers at the
construction site, the construction atmosphere is extremely bustling. 

00:00:15.486 --> 00:00:19.298 
Machinery operating continuously in
items such as embankments, dredging, and 

00:00:19.298 --> 00:00:21.966 
infrastructure renovation are being gradually invested synchronously. 

00:00:22.366 --> 00:00:25.750 
Many people living along the canal
cannot hide their excitement as the 

00:00:25.750 --> 00:00:28.006 
appearance of the area is gradually changing clearly. 

00:00:28.006 --> 00:00:31.568 
It is expected that the project will be
completed on schedule to bring a stream 

00:00:31.568 --> 00:00:35.366 
of clean and beautiful green trees,
contributing to improving the living environment and embellishing the area. 

00:00:36.885 --> 00:00:40.365 
This outside thing is now concreted like
this, it's very different. 

00:00:41.485 --> 00:00:45.430 
Clearly because now if the project is
faster, the facilities here 

00:00:45.430 --> 00:00:46.865 
will change a lot. 

00:00:47.465 --> 00:00:50.225 
First is the road,
traffic will be different. 

00:00:51.065 --> 00:00:54.585 
Maybe the literature will open here,
then everyone's business here will be much better. 

00:00:54.785 --> 00:00:58.753 
Who doesn't expect it to be completed
soon and then it will be even more 

00:00:58.753 --> 00:01:00.605 
beautiful so that everyone can develop together. 

00:01:00.945 --> 00:01:02.465 
Here, the brothers also work relatively well. 

00:01:02.905 --> 00:01:04.605 
Working on time, not working too late. 

00:01:04.605 --> 00:01:10.685 
And at night, I also work at night, but
this side is also greatly affected. 

00:01:11.405 --> 00:01:12.945 
Sometimes the house shakes at night. 

00:01:14.285 --> 00:01:16.845 
You guys dig soil and build piles out here. 

00:01:17.207 --> 00:01:21.230 
If we can build such works, it will be
better for the people, but we like 

00:01:21.230 --> 00:01:22.487 
it even more, it's nothing. 

00:01:23.567 --> 00:01:27.267 
Time feels burned, feels beautiful, and
it starts slowly, when completed it will surely be more beautiful. 

00:01:27.907 --> 00:01:32.619 
It's suitable for me to go out and
travel widely, with a green park, I can 

00:01:32.619 --> 00:01:36.447 
walk, play, and exercise in the morning,
it's okay, it's nothing, it's good. 

00:01:38.171 --> 00:01:41.753 
And then over here, here it has opened
the way already, over there 

00:01:41.753 --> 00:01:43.131 
people have already spread asphalt. 

00:01:43.771 --> 00:01:46.790 
The road has been paved with asphalt,
but on this side it was not before, on 

00:01:46.790 --> 00:01:48.111 
this side it is still being embanked. 

00:01:48.611 --> 00:01:50.231 
They're making a strong move on this road. 

00:01:50.511 --> 00:01:53.964 
New people want the road to be
beautiful, to be given, in general, who 

00:01:53.964 --> 00:01:57.171 
doesn't want, who doesn't want a clean
and beautiful city, green and beautiful. 

00:01:58.294 --> 00:02:01.714 
According to the Thap Phat Chi Minh
Urban Infrastructure Construction Investment Project Management Board, 

00:02:02.114 --> 00:02:06.394 
The overall project progress is assessed
as planned, despite infrastructure relocation, 

00:02:06.394 --> 00:02:10.034 
techniques such as electricity, water,
and hospitals still face many 

00:02:10.034 --> 00:02:11.854 
difficulties due to new regulations. 

00:02:11.854 --> 00:02:15.414 
related to land law and compensation
and ice clearance work. 

00:02:15.954 --> 00:02:19.005 
In the section passing through An Nhon
ward and Binh Loi Trung ward, 

00:02:19.005 --> 00:02:20.414 
the section is about 540m long, 

00:02:20.734 --> 00:02:24.214 
many important items have been completed
such as piles of soil, reinforcement of bamboo shoots, 

00:02:24.214 --> 00:02:26.934 
piles of concrete piles maintaining the
pressure of the embankment wall construction. 

00:02:27.334 --> 00:02:30.594 
The contractor is currently continuing
to deploy the drainage system and technical trenches. 

00:02:30.594 --> 00:02:34.053 
According to the plan, this section is
expected to be technically opened 

00:02:34.053 --> 00:02:35.494 
to traffic in September 2026. 

00:02:35.494 --> 00:02:39.094 
and basically completed in
November 2026. 