00:00:03.438 --> 00:00:06.818 
At the construction site of the indoor
school and secondary school project in 

00:00:06.818 --> 00:00:08.378 
Dac Rong commune, Quang Tri province, 

00:00:08.718 --> 00:00:11.038 
more than 200 officials and workers are working continuously. 

00:00:11.458 --> 00:00:14.848 
With the special feature of the
construction area located next to a high 

00:00:14.848 --> 00:00:17.978 
hillside, creating a construction site
faces many obstacles, requiring time and effort. 

00:00:18.478 --> 00:00:22.398 
Currently, the weather in Dac Rong
commune is hot despite affecting the health of workers. 

00:00:22.398 --> 00:00:25.410 
but create favorable conditions for
construction progress after a long 

00:00:25.410 --> 00:00:27.518 
period of interruption due to prolonged rain. 

00:00:29.194 --> 00:00:34.191 
On that construction site, all our
building blocks here are difficult 

00:00:34.191 --> 00:00:38.734 
parts, bloody parts, dry parts,
difficult parts have overcome everything. 

00:00:39.294 --> 00:00:44.794 
The current progress is about more than
20% of the contract volume value. 

00:00:46.511 --> 00:00:48.681 
According to records, the 3-story
administrative building has completed 

00:00:48.681 --> 00:00:50.851 
the rough construction of the 1st and 2nd floors. 

00:00:51.231 --> 00:00:54.018 
The secondary school building has
completed the rough construction of the 

00:00:54.018 --> 00:00:56.551 
floors, and the teacher dormitory
area has achieved similar progress. 

00:00:57.091 --> 00:00:59.284 
According to the Pre-management
Construction Investment Project 

00:00:59.284 --> 00:01:00.851 
Management Board, in April 2026, 

00:01:00.851 --> 00:01:04.345 
the Dak Rong primary and secondary
boarding school project will complete 

00:01:04.345 --> 00:01:06.251 
the entire reinforced concrete frame structure, 

00:01:06.551 --> 00:01:09.851 
and at the same time deployed wall
construction, carving and construction of technical infrastructure. 

00:01:09.851 --> 00:01:13.446 
In the next 3 months, the unit will
complete all items, install equipment to 

00:01:13.446 --> 00:01:16.271 
hand over and put the project
into use according to plan. 

00:01:17.699 --> 00:01:22.459 
To ensure progress by July, we will put
it into use according to the contracts, 

00:01:23.019 --> 00:01:26.351 
then at the construction site, they have
to increase fish, increase in 

00:01:26.351 --> 00:01:27.739 
time, work day and night. 

00:01:28.679 --> 00:01:32.962 
Materials and materials must be fully
ensured, always fully ensured for 

00:01:32.962 --> 00:01:34.519 
inspection of all tasks. 

00:01:36.171 --> 00:01:40.411 
From mid-November 2025, 3 other
inter-level boarding school projects were also implemented, 

00:01:40.751 --> 00:01:44.731 
including Huong Phung, Thuong Trach and
Dan Hoa primary and secondary boarding schools. 

00:01:45.091 --> 00:01:48.751 
Quang Tri Provincial People's Committee
said that the progress of projects basically meets the set requirements. 

00:01:49.231 --> 00:01:53.191 
According to statistics, 4 projects have
been allocated enough 1,061 billion VND, 

00:01:53.191 --> 00:01:55.171 
reaching 100% of the total investment. 

00:01:55.371 --> 00:02:00.171 
Accumulated disbursement value to date
reached 306,886 million VND. 