The construction site of the extended
Tran Huong Dao Avenue in Lao Cai is 

00:00:06.355 --> 00:00:07.518 
entering the construction acceleration phase. 

00:00:08.138 --> 00:00:11.778 
Signing on the same week of April shows
that many constructions are being deployed simultaneously, 

00:00:12.038 --> 00:00:13.858 
machinery operates continuously on the entire route. 

00:00:14.878 --> 00:00:21.578 
The project is more than 2.5 km long,
implemented in the period 2021-2026. 

00:00:22.018 --> 00:00:24.823 
Total investment of more than 170
billion VND, connecting from the 

00:00:24.823 --> 00:00:26.098 
extended Tran Huong Dao street 

00:00:26.098 --> 00:00:28.498 
to the Ngoai Bo stream area, Gia Phu commune. 

00:00:28.498 --> 00:00:32.290 
Site clearance work is basically
completed with more than 160 households 

00:00:32.290 --> 00:00:34.358 
discussing land fences to serve construction. 

00:00:35.398 --> 00:00:38.220 
Currently, the construction package for
the roadbed and drainage system has 

00:00:38.220 --> 00:00:39.758 
reached about 70% of the volume. 

00:00:39.758 --> 00:00:43.271 
With more than 2.3 km of roadbed
completed, the components of culverts 

00:00:43.271 --> 00:00:46.198 
and drains have been precast
and are being installed synchronously. 

00:00:47.138 --> 00:00:49.578 
According to the construction
contractor, the unit has paved about 

00:00:49.578 --> 00:00:50.798 
450 m of road surface, 

00:00:51.078 --> 00:00:55.028 
There are still about 300 m of K-98 base
being completed and will be 

00:00:55.028 --> 00:00:56.438 
completed in about 20 days. 

00:00:57.326 --> 00:01:03.459 
At my current time, 450m long has been
paved and about 300m is being completed 

00:01:03.459 --> 00:01:04.686 
to K98 Temple. 

00:01:05.086 --> 00:01:09.613 
In the next 20 days, the 300m node to
the K98 elevation will be completed for 

00:01:09.613 --> 00:01:12.726 
compaction and there will be a
plan to proceed with takeoff. 

00:01:13.370 --> 00:01:17.197 
Information from Odea project management
department, Lao Cai Provincial Traffic 

00:01:17.197 --> 00:01:19.110 
Construction Investment Project Management Board. 

00:01:19.510 --> 00:01:23.250 
The investor is closely monitoring the
progress, coordinating with the contractor to remove obstacles. 

00:01:23.336 --> 00:01:26.797 
Faced with the current difficulties
regarding the very high increase in 

00:01:26.797 --> 00:01:28.056 
the price of materials, 

00:01:28.656 --> 00:01:31.116 
then the investor always closely
follows the construction contractor unit, 

00:01:31.556 --> 00:01:36.136 
Commit to accompanying the contractor in
the implementation process to promptly remove difficulties. 

00:01:36.136 --> 00:01:38.776 
to ensure the contractor's progress as
agreed in the signed contract. 

00:01:39.499 --> 00:01:43.071 
When put into use, the project will have
infrastructure completion and urban 

00:01:43.071 --> 00:01:44.559 
space expansion for the province. 