Component projects 2, 3 and 4 of the
Chau Doc-Can Tho-Soc Trang expressway 

00:00:09.094 --> 00:00:12.100 
section passing through Can Tho are
currently implementing 11 bidding 

00:00:12.100 --> 00:00:15.407 
packages, including 10 installed vehicle
packages and 1 traffic safety package. 

00:00:16.047 --> 00:00:19.447 
To date, the construction volume has
reached about 54% of the total contract value. 

00:00:20.067 --> 00:00:23.253 
In which, basic bridge items have
reached and exceeded the schedule. 

00:00:23.253 --> 00:00:27.018 
However, some sections of the route are
still slow due to dependence on 

00:00:27.018 --> 00:00:28.467 
foundation material sources, especially sand. 

00:00:29.601 --> 00:00:34.383 
The quantity of sand provided for this
expressway project, based on the value 

00:00:34.383 --> 00:00:38.061 
assessment, today also ensures the
quantity to serve the expressway. 

00:00:38.521 --> 00:00:42.637 
But currently the difficulty is focusing
on the solution of increasing 

00:00:42.637 --> 00:00:47.127 
exploitation in terms of means,
exploiting the sand mines that we have 

00:00:47.127 --> 00:00:51.617 
had quantitative resources to ensure
according to the progress that Can Tho 

00:00:51.617 --> 00:00:56.482 
city is directing monthly to investors,
which has set the monthly progress from 

00:00:56.482 --> 00:00:59.101 
now until the end of next month. 

00:01:00.042 --> 00:01:03.357 
At provincial road projects that are
lacking sand filling sources, Mr. Le 

00:01:03.357 --> 00:01:05.842 
Nhat Thu, Deputy Head of Project Management Board 2, 

00:01:06.322 --> 00:01:08.545 
The project management board for
investment in construction of transport 

00:01:08.545 --> 00:01:10.322 
and agricultural works of Can Tho city said, 

00:01:10.802 --> 00:01:13.624 
The unit really hopes that localities
will have sand supply sources, 

00:01:13.624 --> 00:01:15.162 
supporting foundation material for the project. 

00:01:16.290 --> 00:01:20.990 
In general, there are two core and most
important issues of the project. 

00:01:21.110 --> 00:01:24.730 
The first is about site clearance work. 

00:01:24.970 --> 00:01:30.130 
The second task is the support work for
sand and stone material sources. 

00:01:30.710 --> 00:01:36.546 
The provinces with a lot of material
sources are sand material sources and 

00:01:36.546 --> 00:01:38.790 
stone mines supporting Can Tho. 

00:01:38.790 --> 00:01:43.750 
That's how you want it to be, that's how
you can speed up the construction progress. 

00:01:45.017 --> 00:01:48.604 
Early removal of difficulties in sand
sources and ensuring sufficient 

00:01:48.604 --> 00:01:52.192 
foundation material will be key factors
to accelerate construction progress, 

00:01:52.192 --> 00:01:56.497 
avoid delays and ensure projects are
completed on schedule in Can Tho. 