On June 6, the Binh Duong Provincial
Traffic Construction Investment Project Management Board 

00:00:07.717 --> 00:00:12.137 
is speeding up the construction progress
of Binh Goi Bridge, one of the important projects 

00:00:12.137 --> 00:00:13.937 
under the Ho Chi Minh City Ring Road 3 project. 

00:00:14.257 --> 00:00:17.687 
This project has a total investment of
nearly 600 billion VND, and 

00:00:17.687 --> 00:00:19.117 
construction started in October 2023. 

00:00:19.717 --> 00:00:23.320 
Binh Goi Bridge is 1 km long, with a
scale of 4 bus villages, and the 

00:00:23.320 --> 00:00:24.897 
expressway is designed according to highway standards, 

00:00:25.097 --> 00:00:29.417 
reach 100 km/h. The project has 4
wheels, 4 suction trucks and 2 barges. 

00:00:29.417 --> 00:00:32.785 
Currently, the construction units are
maintaining 48 workers, divided into 2 

00:00:32.785 --> 00:00:34.317 
shifts with 4 construction teams. 

00:00:34.657 --> 00:00:38.597 
After more than 1 year of construction,
the total volume of the project has reached over 75%. 

00:00:38.597 --> 00:00:42.785 
In mid-June 2025, the bridge will be
closed and the Binh Goi Bridge project 

00:00:42.785 --> 00:00:46.077 
will be technically opened to traffic
at the end of 2025. 

00:00:46.505 --> 00:00:51.390 
The progress of the project like this
has been more than 300 days and the 

00:00:51.390 --> 00:00:53.345 
total new output value is reached 

00:00:53.345 --> 00:01:01.085 
is 75%, expected to be between and enter
the construction site on June 15 

00:01:01.085 --> 00:01:04.791 
will be determined to try hard for the
workers, and by the end of 2025, the 

00:01:04.791 --> 00:01:06.645 
entire technical traffic will be open to traffic. 

00:01:08.560 --> 00:01:11.880 
The Binh Duong Province Traffic
Construction Investment Project Management Board also informed, 

00:01:12.180 --> 00:01:15.924 
Currently, 99% of the site is available
for the entire Phap Chinh Minh Ring 

00:01:15.924 --> 00:01:17.260 
Road project through Binh Duong. 

00:01:17.660 --> 00:01:20.689 
The units are urgently constructing,
aiming to put the project 

00:01:20.689 --> 00:01:21.900 
into operation in 2026. 