WEBVTT

00:00:03.457 --> 00:00:06.801 
The Sano Bridge belongs to the 1st
Package of component 3 projects, Chau 

00:00:06.801 --> 00:00:09.117 
Doc highway-Ngo Tho-Soc Moon, section passing Hau Giang province. 

00:00:09.637 --> 00:00:13.217 
Although this bridge has been installed
12 out of 12 beats, exceeding the set 

00:00:13.217 --> 00:00:16.797 
progress, the path has not been able to
be constructed due to sand shortage. 

00:00:17.598 --> 00:00:21.418 
The biggest difficulty it is still the
problem is the lack of small sand. 

00:00:21.658 --> 00:00:26.333 
To reach the progress of this project,
there must be enough of about 6,000 

00:00:26.333 --> 00:00:29.338 
cubic meters of sand per
day on this project. 

00:00:29.878 --> 00:00:38.138 
But now it is only about this project
about 1,500 to 2,000 blocks per day. 

00:00:38.638 --> 00:00:41.558 
That is only a third of the magic. 

00:00:42.455 --> 00:00:45.335 
Regarding the shortage of sand, Bi Thu
Provincial Party Committee of Hau Giang 

00:00:45.335 --> 00:00:48.659 
Dong Van Thanh said that he would talk
to An Giang province to transfer the 

00:00:48.659 --> 00:00:50.875 
sand temporarily borrowed to Can Tho - Ca Mau Expressway. 

00:00:51.736 --> 00:00:56.419 
Regarding the sand material, we will
also report this situation to 

00:00:56.419 --> 00:00:57.696 
the Prime Minister. 

00:00:58.396 --> 00:01:03.036 
At the same time, it is also proactive
to discuss with An Giang province. 

00:01:03.836 --> 00:01:10.423 
To continue to be one is to transfer the
sand that has temporarily borrowed, 

00:01:10.423 --> 00:01:12.776 
transferred to the vertical axis. 

00:01:13.256 --> 00:01:19.361 
The second is that the missing part
continues to be the sand mine of An 

00:01:19.361 --> 00:01:21.396 
Giang Chicken and then support. 

00:01:21.736 --> 00:01:23.136 
For Hau Giang. 

00:01:23.731 --> 00:01:26.799 
It is known that the Chau Doc highway
project-Ngan Tho-moon needs a total of 

00:01:26.799 --> 00:01:28.771 
about 31 million cubic meters of sand to complete. 

00:01:29.151 --> 00:01:32.410 
However, until early March, the new
units determined the supply of 

00:01:32.410 --> 00:01:33.891 
about 23 million cubic meters, 

00:01:34.251 --> 00:01:37.991 
Meanwhile, 8 million cubic meters still
lacked the supply. 