00:00:04.469 --> 00:00:08.602 
To ensure the progress of the 500 kV Lao
Cai - Vinh Yen transmission line project 

00:00:08.602 --> 00:00:10.669 
starting in February and completing before September 2, 

00:00:11.149 --> 00:00:14.749 
The work of clearing the ice surface in
Bao Yen district with 67 pole positions 

00:00:14.749 --> 00:00:16.909 
on a 34 km long route is being accelerated. 

00:00:17.309 --> 00:00:21.296 
This is one of the biggest challenges of
the project, requiring great efforts 

00:00:21.296 --> 00:00:22.829 
from local authorities and people. 

00:00:24.348 --> 00:00:29.590 
The meaningful work of the country and
my family is also in the relocation area 

00:00:29.590 --> 00:00:30.988 
of ​​Ve Dien street. 

00:00:31.808 --> 00:00:38.322 
My family also supports and coordinates
with our brothers to resolve the issue 

00:00:38.322 --> 00:00:40.828 
quickly and complete it sooner. 

00:00:41.324 --> 00:00:45.944 
Invite to the commune for direct
dialogue, local religion. 

00:00:46.104 --> 00:00:49.084 
I met at each family association to
propagate and mobilize the people. 

00:00:49.224 --> 00:00:52.977 
Through propaganda and mobilization, the
people also fully agreed with the 

00:00:52.977 --> 00:00:55.024 
investment policy to build the project. 

00:00:56.123 --> 00:00:59.061 
Bao Yen district has successfully
completed the work of statistics and 

00:00:59.061 --> 00:01:00.663 
site clearance at 67 pole locations. 

00:01:01.143 --> 00:01:03.583 
ready to sell the premises to investors in the coming days. 

00:01:04.243 --> 00:01:07.643 
With a determined spirit, the locality
is focusing on liberating the route corridor. 

00:01:07.643 --> 00:01:10.023 
to ensure the progress of the 500 kV project. 

00:01:13.117 --> 00:01:17.437 
Find land to arrange resettlement for
households to combine to ensure the 

00:01:17.437 --> 00:01:20.317 
correct progress, time, and
handover of the site. 

00:01:21.017 --> 00:01:26.217 
To do that, we mobilized all civil
servants of the industry as well 

00:01:26.217 --> 00:01:27.817 
as commune land officials. 

00:01:27.817 --> 00:01:30.937 
and a number of related departments. 

00:01:30.937 --> 00:01:37.172 
During the day we are going to count the
prices and at night we have a group of 

00:01:37.172 --> 00:01:40.637 
brothers at home doing the pricing
to achieve the plan. 

00:01:41.568 --> 00:01:45.308 
With high determination, Lao Cai
province has been striving to overcome all difficulties. 

00:01:45.308 --> 00:01:48.973 
to complete ahead of schedule the target
of handing over clean site for the 500 

00:01:48.973 --> 00:01:50.928 
kV Lao Cai Vinh Yen transmission line project. 

00:01:51.508 --> 00:01:55.094 
It is expected that by this March, the
entire corridor will be handed over 4 

00:01:55.094 --> 00:01:56.528 
months earlier than the original plan. 