To ensure electricity supply for the
construction of Long Thanh airport and 

00:00:07.065 --> 00:00:09.268 
after Long Thanh airport comes into operation, 

00:00:09.668 --> 00:00:14.679 
In June 2024, Dong Nai Electricity One
Member Co., Ltd. started construction of 

00:00:14.679 --> 00:00:18.148 
the 110kV Long Thanh airport
substation and connecting line. 

00:00:18.268 --> 00:00:22.729 
The project has a total investment of
119 billion VND and is expected to be 

00:00:22.729 --> 00:00:25.108 
put into acceptance and energized in November 2024. 

00:00:30.001 --> 00:00:32.841 
Since the Long Thanh airport project
started, Long Thanh Power Company has 

00:00:32.841 --> 00:00:34.261 
belonged to Dong Nai Power Company. 

00:00:34.261 --> 00:00:37.176 
has coordinated with the state operating
Long Thanh airport to ensure 

00:00:37.176 --> 00:00:38.501 
stable and continuous power supply, 

00:00:38.761 --> 00:00:42.141 
serving construction activities on
project sites with supplied electricity output 

00:00:42.141 --> 00:00:46.326 
for Long Thanh airport construction
activities on average about 630,330 

00:00:46.326 --> 00:00:47.581 
kWh per month. 

00:00:47.901 --> 00:00:50.941 
However, to ensure power supply as soon
as Long Thanh airport comes into operation, 

00:00:50.941 --> 00:00:55.347 
On June 6, 2024, Dong Nai Power Company
officially started construction of the 

00:00:55.347 --> 00:00:57.381 
110kV Long Thanh airport station project. 

00:00:57.381 --> 00:01:00.861 
and connection lines with a total
investment of 119 billion VND. 

00:01:01.221 --> 00:01:04.205 
In addition, when put into operation,
the 110kV Long Thanh airport power 

00:01:04.205 --> 00:01:06.941 
station will also contribute to reducing
the 22kV power supply radius. 

00:01:07.741 --> 00:01:10.483 
Reduce total loss, ensure voltage
quality, improve reliability, supply 

00:01:10.483 --> 00:01:11.701 
electricity to neighboring areas. 

00:01:11.817 --> 00:01:15.587 
Currently, we are working hard to
complete the power connection according 

00:01:15.587 --> 00:01:16.957 
to the company's instructions. 

00:01:17.077 --> 00:01:20.677 
Construction and installation of
connection lines are underway. 

00:01:21.197 --> 00:01:25.164 
And today is the power cut off of Binh
Son branch line to connect to main line 

00:01:25.164 --> 00:01:26.797 
20 to serve the airport power supply. 

00:01:27.595 --> 00:01:32.395 
From the perspective of supervision
consultants, the first is to meet the 

00:01:32.395 --> 00:01:33.995 
progress of the project. 

00:01:33.995 --> 00:01:39.575 
also requires the contractor to focus on
human resources and machinery to meet 

00:01:39.575 --> 00:01:45.295 
and along with that also goes along with
the quality of the project. 

00:01:45.815 --> 00:01:49.675 
The weather is generally rainy weather. 

00:01:49.675 --> 00:01:55.081 
So we also try to overcome that
situation to bring the 

00:01:55.081 --> 00:01:56.555 
project to progress. 

00:01:57.363 --> 00:02:01.248 
In phase 1, the substation section was
built with a transformer with a 

00:02:01.248 --> 00:02:02.743 
total capacity of 40 MvA. 

00:02:03.083 --> 00:02:06.083 
The line consists of 2 circuits with
a total length of 3.8 km. 

00:02:06.423 --> 00:02:08.980 
Up to now, 70% of the construction
volume of the power line has been 

00:02:08.980 --> 00:02:11.903 
completed, and 70% of the construction
volume of the station installation vehicle has also been completed. 

00:02:11.943 --> 00:02:17.129 
In phase 2, machine 2 with a capacity of
40 MvA will be installed, increasing the 

00:02:17.129 --> 00:02:21.343 
total capacity of the 110 kV Long Thanh
transformer station to 80 MvA. 

00:02:21.543 --> 00:02:25.123 
Phase 1 is expected to be
energized in November 2024. 

00:02:25.123 --> 00:02:29.163 
Phase 2 will be accepted and put into
operation in the third quarter of 2025. 

00:02:30.100 --> 00:02:33.140 
Trying to speed up progress
to meet investor's needs. 

00:02:33.380 --> 00:02:37.900 
Current workers are 25-27 people. 

00:02:38.860 --> 00:02:44.583 
Machinery includes site-clearing
equipment such as excavators, cranes, 

00:02:44.583 --> 00:02:48.160 
trailers and some hand-held equipment. 

00:02:48.747 --> 00:02:51.763 
According to Dong Nai Electricity
Company, the project of 110kV station of 

00:02:51.763 --> 00:02:54.527 
Long Thanh airport and connecting line
phase 2 has been completed. 

00:02:54.527 --> 00:02:57.477 
The power supply for Long Thanh airport
will be guaranteed to be safe, 

00:02:57.477 --> 00:03:00.427 
continuous and of good quality as soon
as the airport comes into operation. 